IHS Home PageIHS
  • Home
  • IHS Capabilities
    IHS Capabilities
    • IHS Capabilities Overview
    • Capabilities
    • Energy & Power
    • Design & Supply Chain
    • EHS & Sustainability
    • Defense, Risk & Security
    • Commodities, Pricing & Cost
    • Country & Industry Forecasting
    • IHS Experts
    • Global Reach
    • Recent Topics
    • Q&A
    • Energy & Power

      Energy & Power

      IHS helps energy firms make confident decisions with full coverage of fuel types and markets More

    • Global Reach

      Global Reach

      With nearly 100 offices around the globe, provides a global network for clients More

  • Industry Solutions
    Industry Solutions
    • Industry Solutions Overview
    • Aerospace & Defense
    • Agriculture
    • Renewable Energy
    • Automotive
    • Chemicals
    • Construction
    • Consumer & Retail
    • Electronics & Telecommunications
    • Energy Oil & Gas
    • Financial
    • Government
    • Healthcare & Pharmaceutical
    • Metals & Mining
    • Military & Security
    • Power & Utilities
    • Shipping & Transportation
    • Aerospace & Defense

      Aerospace & Defense

      Data and analysis for Aerospace and Defense lifecycle, from program conception to retirement More

    • Metals and Mining

      Metals and Mining

      IHS Metals and Mining experts deliver market knowledge and updates in operational safety regulations More

  • Products & Services
    Products & Services
    • Products & Services Overview
    • Energy & Power
    • Oil & Gas Information and Analytical Tools
    • IHS CERA: Energy Strategy
    • IHS Herold: Energy Company & Transactions Valuations
    • Coal Information & Insight: IHS McCloskey
    • Renewable Energy: IHS Emerging Energy Research
    • Design & Supply Chain
    • Industry Standards & Regulations
    • Product Design, Sourcing & Logistics
    • Maintenance, Repair & Ops Management (MRO)
    • EHS & Sustainability
    • Environmental, Health and Safety & Sustainability
    • Defense & Risk & Security
    • IHS Jane's: Defense & Security Intelligence and Analysis
    • Maritime Intelligence & Publications: IHS Fairplay
    • Commodities, Pricing & Cost
    • IHS Global Insight: Pricing & Purchasing
    • IHS CERA: Capital Costs
    • Country & Industy Forecasting
    • IHS Global Insight: Country & Industry Forecasting
    • Automotive Forecasting: IHS Automotive
    • IHS Global Scenarios
    • Other Services
    • Consulting & Advisory Services
    • IHS CERA

      IHS CERA

      Leading strategy advisors to international energy companies, governments and financial institutions More

    • Standards & Regulations

      Standards & Regulations

      IHS provides technical standards, codes and specifications and the tools to manage critical data More

    • EHS&S Solutions

      EHS&S Solutions

      IHS helps companies meet EHS&S goals with the most deployed enterprise software solution More

  • News & Analysis
    News & Analysis
    • News & Analysis

      News & Analysis

      IHS covers global industry and economic news and analysis to advance client business decisions More

    • News & Analysis Overview
    • Industry & Economics
    • Energy
    • Defense & Security
  • Events
    Events
    • World Wind Energy China 2011

      World Wind Energy China 2011

      Visit IHS at the World Wind Energy Summit China 2011 in Beijing, China More

    • APPEA Conference 2011

      APPEA Conference 2011

      IHS supports the Southern hemisphere's largest annual upstream oil and gas event, APPEA. More

    • Events Overview
    • IHS Events
    • Member Events
    • Industry Events
    • Training & User Groups
    • Webcasts
  • About
    About
    • Contact Us

      Contact Us

      IHS takes pride in putting customers first and making sure that we keep you informed and updated More

    • Social Responsibility

      Social Responsibility

      We care about improving quality of life for our customers, colleagues and communities More

    • About IHS Overview
    • Contact Us
    • Customer Care
    • IHS at a Glance
    • Corporate Social Responsibility
    • Executive Team
    • Investor Relations
    • Press Room
    • Careers

News & Analysis

  • Home
  • News & Analysis
  • News
Print Page Email Page Smaller Text Larger Text

News and Analysis

  • IHS News Archive

FERC Finalizes Electric Transmission Siting Rule

November 27, 2006 // Published as a news service by IHS

Power & Utilities Documents
The IHS Utility Standards Collection includes bulletins, codes, recommended practices and standards from ASTM, API, IEEE, ANS, AGA, ASME, NEMA, ASCE, ISA and other groups.

Documents cover electrical systems, pressure vessels, piping, valves, pumps, generators, welding, etc.

To learn more, and for a free quote, please complete the form below.
Utility Standards Collection
First Name:

Last Name:

Email Address:
The U.S. Federal Energy Regulatory Commission (FERC) approved a final rule governing the filing requirements and procedures for entities asking the FERC to exercise its supplemental authority to site interstate transmission facilities under the Energy Policy Act of 2005 (EPAct).

FERC Chairman Joseph T. Kelliher said, "One of the major goals of the landmark Energy Policy Act of 2005 was strengthening our nation's power grid. Today, the commission takes final action to implement the transmission siting provisions of the act.

"Our approach was very respectful of state authority. As a practical reality, I would expect states will continue to site the vast bulk of transmission projects. Congress did not provide for exclusive federal siting authority, and we will use our authority to supplement state transmission siting."

The biggest change from the proposed rule relates to the initiation of prefiling at the FERC. Under the proposed rule, an applicant is barred from making a formal application for a federal construction permit until one year after initiation of a state proceeding.

But prefiling could be initiated earlier, and could overlap with the state siting proceeding. In response to state concerns, the final rule bars both a formal application and the initiation of prefiling within one year of initiation of a state proceeding.

EPAct provides for supplemental federal authorization of certain electric transmission facilities in national interest electric transmission corridors designated by the secretary of energy. In these corridors with power grid capacity constraints or congestion that adversely affects consumers, the FERC may issue permits to construct or modify electric transmission facilities if it finds:

  • A state in which a facility is located does not have siting authority or state law does not consider interstate benefits.
  • The applicant for the facility is a transmitting utility but does not qualify to apply for siting approval in the state because the applicant does not serve end-use customers in the state.
  • A state with siting authority either withholds approval for more than one year after the application is filed or one year after the designation of the relevant corridor, whichever is later.
  • The state conditions its approval such that it will not significantly reduce transmission congestion or it is not economically feasible.

The final rule addresses comments received from 51 entities in response to a June 16, 2006 notice of proposed rulemaking. The final rule largely affirms the approach outlined in the proposed rule.

A proposal to build or expand electric transmission facilities must:

  • Apply to facilities that will be used for transmission in interstate commerce.
  • Be consistent with the public interest and enhance energy independence.
  • Significantly reduce transmission congestion in interstate commerce.
  • Protect or benefit consumers.
  • Be consistent with national energy policy and enhance energy infrastructure.
  • Maximize, to the extent reasonable and practicable, existing towers or structures.

The pre-filing process includes consultation with the director of the Office of Energy Projects (OEP) to determine project eligibility for pre-filing, the start of environmental review under the National Environmental Policy Act (NEPA), numerous public participation opportunities and a determination by the director of OEP that an application is ready to be filed for FERC consideration.

Once an application is filed, the rule requires public notification of the application, issuance and solicitation of comments on the draft environmental document, preparation and issuance of a final environmental document, a review of the record and issuance of a final decision by the FERC.

The following are among the significant decisions the FERC made in the final rule:

  • The FERC pre-filing process will not commence until one year after an application has been filed for state review.
  • The FERC declined to establish specific criteria on how it will determine whether states have authority to approve the siting of transmission facilities or consider interstate benefits, deciding instead to make these determinations on a case-by-case basis.
  • Entities seeking to invoke FERC jurisdiction on the basis of a state's failure to act will be required to pursue the requisite application with the state one year prior to commencing pre-filing at the FERC.
  • FERC will consider all information filed with the states as part of its review of the proposed project. However, the FERC is required under NEPA to conduct its own, independent review of potential environmental impacts.
  • The FERC clarified how it intends to implement its notification requirements with respect to entities that must be notified regarding the project, and how an interested person may access information and participate in FERC proceedings.
  • The FERC eliminated from the final rule a proposed property value impact analysis, concluding that concerns regarding the accuracy of such studies could delay the development of transmission projects.
  • The FERC will convene a number of regional technical outreach conferences after issuance of the final rule.

The final rule - Regulations for Filing Applications for Permits to Site Interstate Electric Transmission Facilities - takes effect 60 days after publication in the Federal Register.

Source: U.S. Federal Energy Regulatory Commission (FERC).

IHS Capabilities

  • Energy & Power
  • Design & Supply Chain
  • EHS & Sustainability
  • Defense, Risk & Security
  • Commodities, Pricing & Cost
  • Country & Industry Forecasting

Industry Solutions

  • Aerospace & Defense
  • Agriculture
  • Automotive
  • Chemicals
  • Construction
  • Consumer & Retail
  • Electronics & Telecommunications
  • Energy Oil & Gas
  • Financial
  • Government
  • Healthcare & Pharmaceuticals
  • Metals & Mining
  • Military & Security
  • Shipping & Transportation

Products & Services

  • Industry Standards & Regulations
  • Product Design, Sourcing & Logistics
  • Maintenance, Repair & Ops Management (MRO)
  • Environment, Health and Safety & Sustainability
  • Maritime Intelligence & Publications: Fairplay
  • IHS Global Scenarios
  • Consulting & Advisory Services
  • About IHS
  • Contact Us
  • Customer Care
  • Careers
  • Investors
  • Site Map
  • A-Z Product Index
  • Accessibility
  • Privacy Policy
  • Legal Statement 2011 IHS Inc. All Rights Reserved.